We are developing a new 132kV electricity connection that will link the proposed Nant Mithil Energy Park in the Radnor Forest area in Powys to the proposed National Grid substation at Llandyfaelog in Carmarthenshire.
Thank you to everyone who took part in our two rounds of public consultation in Spring 2023 and Spring 2024. Your input is continuing to help us shape a project that works for the people who live, work, and spend time in the areas around our proposals. As a result of these contributions, as well as further assessments and feedback from technical stakeholders, we are proposing some changes to the Towy Usk Grid Connection.
The proposed changes include:
- realigning the route into less prominent terrain near Aberedw Hill;
- increasing the distance of the proposed connection from Llanwrda, Llandovery and Cwrt Henri; and
- reducing potential impacts on ancient woodland, priority habitat, the River Towy flood zone and key heritage features.
Changes we are progressing also include repositioning the route to lessen effects near Cilmeri and Glan Irfon, extending the underground section near Llanarthney, and adjusting the proposed route alignment to reflect proposed development at Nantycaws.
View our proposed changes to the Towy Usk Grid Connection
If you would like to view the latest changes proposed to the Towy Usk Grid Connection route alignment, these can be viewed using the Overview and Interactive map. Further detailed information on these updates is also available on Our Proposals page.
If you have any questions about the information we’re sharing, please call us on 0800 3777 339 or email us at info@greengentowyusk.com.